Laser-guided base preparation.
Laser-guided grading was used on the compacted stone base, establishing the foundation for the concrete placement.

Industrial concrete replacement
More than 14,000 square feet of concrete replaced. Full crane and truck traffic restored on schedule.
The assignment / OmniSource
OmniSource needed an exterior concrete work area replaced without losing a day of production. KurtzMeo had a 72-hour window to remove and replace more than 14,000 square feet and return the area to full crane and truck use.
The project also presented an opportunity to revisit the planned slab design. Engineering, site preparation, concrete placement, and the return-to-service schedule all needed to work together.
Engineering the value
After an engineering review confirmed that structural steel fiber reinforcement would meet the design loads, we reduced the planned slab thickness by two inches. The savings brought OmniSource well under its capital allocation, freeing up budget for other needs that season.
That decision was specific to this project’s design. Steel fiber reinforcement and a thinner slab are not interchangeable specifications for every site; loads, support conditions, and engineering requirements govern the design.
Building around the operation
The operating deadline shaped the construction approach.
Laser-guided grading was used on the compacted stone base, establishing the foundation for the concrete placement.
A 3D laser screed supported controlled placement across the large industrial work area.
A concrete mix designed for a 24-hour return to service helped meet the 72-hour removal-and-replacement window.
On site
The result
The site reopened to full crane and truck traffic on schedule, without losing a day of production. The engineering savings also left room in OmniSource’s capital budget for other needs that season.
For an operating business, the concrete is only part of the assignment. The plan has to account for the work that happens on it.
Explore our commercial concrete servicesPlanning a concrete replacement?
Tell us about your site, equipment loads, available shutdown window, and capital budget.